AFE 1007, Para, Minnesota, 1905. Place Marker Pipe at Gasoline Plant. Interstate Commerce Commission Account Number 19, Fueling Stations. Cost: $22. Series GM. Lines East. Other Subject Categories: Servicing Facilities, Other
AFE 1007, Para, Minnesota, 1905. Place Marker Pipe at Gasoline Plant. Interstate Commerce Commission Account Number 19, Fueling Stations. Cost: $22. Series GM. Lines East. Other Subject Categories: Servicing Facilities, Other
AFE 10110, Para, Minnesota, 1904. Remove Pit Track and Lay New Track at Kelly Lake Pit. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $139. Series I. Lines East. Other Subject Categories: Track, Industry
AFE 11043, Para, Minnesota, 1905. Temporary - Install and Remove at Para Pit. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $57. Series I. Lines East. Other Subject Categories: Track, Industry
AFE 1140, Para, Minnesota, 1906. with Drain Boxes. Interstate Commerce Commission Account Number 14, Crossings. Cost: $80. Series GM. Lines East. Other Subject Categories: Crossings, Private
AFE 11504, Para, Minnesota, 1905. 2100' West of West Switch. Interstate Commerce Commission Account Number 14, Crossings. Cost: $176. Series I. Lines East. Other Subject Categories: Crossings, Public
AFE 12621, Para, Minnesota, 1906. Erect 38130' Near Station. Interstate Commerce Commission Account Number 13, Fences, Snowsheds and Signs. Cost: $925. Series I. Lines East. Other Subject Categories: Fences, Right of Way
AFE 1451, Para, Minnesota, 1906. 1 1/2 Mile West. Interstate Commerce Commission Account Number 13, Fences, Snowsheds and Signs. Cost: $198. Series GM. Lines East. Other Subject Categories: Fences, Right of Way
AFE 15276, Para, Minnesota, 1908. Construct One Mile North. Interstate Commerce Commission Account Number 14, Crossings. Cost: $78. Series I. Lines East. Other Subject Categories: Crossings, Private
AFE 18009, Para, Minnesota, 1910. Remove - Para Pit. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $0. Series I. Lines East. Other Subject Categories: Track, Industry
AFE 20961, Para, Minnesota, 1922. Remove 4350' Track Leave 500' for Industry Track, Remove Double Crossovers One 218' Long and 213' Long. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $1600. Series II. Lines East. Other Subject Categories: Track, Passing