Great Northern Railway Authorization for Expenditure (AFE) 35267, Mesabi Chief Mine, Minnesota, 1927.

AFE 35267, Mesabi Chief Mine, Minnesota, 1927. Construct Main Spur 3909' , Storage Track 1600' , and 2 Turnouts 120'. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $17200. Series II. Lines East. Other Subject Categories: Track, Industry

Great Northern Railway Authorization for Expenditure (AFE) 38551, Mesabi Chief Mine, Minnesota, 1928.

AFE 38551, Mesabi Chief Mine, Minnesota, 1928. Constrct Main Spur 6659' , Run Around Track 1477' and Second Tail Track 678 to Washing Plant. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $32340. Series II. Lines East. Other Subject Categories: Track, Industry

Great Northern Railway Authorization for Expenditure (AFE) 48370, Mesabi Chief Mine, Minnesota, 1934.

AFE 48370, Mesabi Chief Mine, Minnesota, 1934. Relay with Secondhand Track Present Spur and Construct Stockpile Track # 1 1450' Long, and Stockpile Track # 2 900' Long to Serve Washing Plant. Interstate Commerce Commission Account Number 9, Rails. Cost: $5200. Series II. Lines East. Other Subject Categories: Track Maintenance, Rail

Great Northern Railway Authorization for Expenditure (AFE) 60.0789, Mesabi Chief Mine, Minnesota, 1960.

AFE 60.0789, Mesabi Chief Mine, Minnesota, 1960. Cosntruct Stockpile Track 1600' Long, Rearrange Present Stockpile Track. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $12451. Series II. Lines East. Other Subject Categories: Track, Industry

Great Northern Railway Authorization for Expenditure (AFE) 64487, Mesabi Chief Mine, Minnesota, 1942.

AFE 64487, Mesabi Chief Mine, Minnesota, 1942. Construct 100' Turnout From Mississippi Mine Spur and Remove 2773' of Mesabi Chief Mine Direst Ore Yard. Interstate Commerce Commission Account Number 12, Track Laying and Surfacing. Cost: $800. Series II. Lines East. Other Subject Categories: Track, Industry